A number of roadways in Park Valley are being paved
from Monday, May 15, until Friday, May 19. The paving work begins at 7:30 a.m.
every morning. Here is the daily schedule listing the affected streets:
May 15:
Rogers
Loop
May 16 and 17:
Whipple
driveways and U-shaped turnouts
24th
Drive w with parking area
24th
Avenue with cul de sac
May 18 (affecting one lane of the following streets):
19th
Avenue and Whipple mainline
20th
Avenue full paving
23rd
from SR260 → Stratton → 21st Avenue
Stratton
from East end → 21st Avenue
May 19 (the May 18 plan will be repeated for the
opposite lane):
19th
Avenue and Whipple mainline
20th
Avenue full paving
23rd
from SR260 → Stratton → 21st Avenue
Stratton
from East end → 21st Avenue
We
appreciate your patience while these road improvements are being done. If you
have any questions, please call City Engineer Shane Hemesath at 537-4090.